USP Initiatives

The National Fiberisation and Connectivity Plan 1 (NFCP 1)

The NFCP 1 involves the deployment of 152 towers and the provisioning of cellular mobile broadband services in 93 mukim.
These comprises of eight (8) states namely Johor, Kedah, Kelantan, Negeri Sembilan, Pahang, Perak, Terengganu and Sabah.

Cost of project: RM290 million

152 towers to be deployed for public cellular service provisioning


Deployment of Towers by State

This project, which was tendered out earlier as Ubiquitous 1 on 31 May 2017, was reviewed by the Commission with the aim of revising to its specifications to fit into the targets set in the NFCP blueprint. Under NFCP 1, the project was separated into two (2) parts, namely Parts 1 and 2.

PART 1
Scope of work
  • To supply, deliver and install tower(s) and its ancillaries, for the purposes of the provisioning of public cellular services.
Successful Licensees

Edotco Malaysia Sdn Bhd

113 sites @ 75%

FGV Prodata Systems Sdn Bhd

39 sites @ 25%
2020
  • 23 January 2020
    • Issuance of Notification of Approval (letters of award) to successful licensees
  • 15 February 2020
    • Commencement date of the project for Part 1 DUSPs
  • February 2021
    • Target for completion of project (12 months – 146 sites)
  • February 2022
    • Target for completion of project (24 months – 6 sites for fiberisation)
PART 2
Scope of work
  • To design, supply, install, test, commission and operate network service equipment and services. It is also responsible to provide minimum 3G and 4G services with an average speed of 30Mbps, via a Radio Access Network (RAN) sharing solution.
Successful Licensees

Maxis Broadband Sdn Bhd

102 sites @ 67%

U Mobile Sdn Bhd

50 sites @ 33%

The Part 1 licensees are responsible to build the towers within six (6) months from the commencement date of the project which was on 15 February 2020. The Part 2 licensees will install radio communications equipment and provide the network service for the provisioning of public cellular services within six (6) months after handover of completed sites from the Part 1 licensees.

For six sites, the Part 2 service provider has been granted a duration of eighteen (18) months to complete the work involved, as these sites are particularly remote, and fiberisation in these locations is a challenge.

The list of sites are as shown below.

NO. STATE CLUSTER SITE ID SITE NAME
1. Kedah C02 FC1_019 Ladang Kim Seng, Batu 5
2. Kelantan C03 FC_024 Kg Meranto 2
3. Pahang C06 FC1_065 Pos Lemoi
4. Pahang C06 FC1_066 Kg Telimau
5. Pahang C07 FC1_072 Kg Pasir Durian
6. Terengganu C13 FC1_149 Kg Pak Sik

List of Sites Granted Duration of 18 Months

Download PDF